Late October Update

Got a lot of little stuff done at the end of October!  Most exciting is starting the flooring 🙂

There will be an open house in about a month at Newport Hardware. Details soon!

Early October Progress

We had another trip to prepare for, so in went the stairs/ladder and we finished up the exterior paint (aside from the door and touch-ups).  After getting back from the northern VA adventures, it was time to finish the propane lines!  Finally we could test the water heater, oven/stove, and the Newport P9000.  As much as I wanted a woodstove (and still have the one I bought sitting in storage), this little heater is a good option for tiny houses because of how little clearance it needs around itself.  I ended up buying the woodstove from myself to save for another house down the road 🙂

Besides all these pictures, I have a video treat for you all coming up.  If only I could get it to load…I took today off from work, so I’ll do my best to post the vid today sometime in between my various construction projects.

Build Day 24 (6/3/12)

A short workday but we managed to install the front door.  It’s steel with a venting window to help cool down the house since I’m not putting in A/C.  The original plans called for two windows on either side of the door, but I really wanted to use the space on the inside for storage rather than for windows.  I think this meets the window/wall space requirement I had in my head quite nicely.  As for hardware, I’m going to scrounge around the ReStore but I’ll probably have to get a new knob and deadbolt set.  Boooo!

The installation itself was easier than I thought.  I caulked the floor underneath the door to seal out the elements and such, then we popped in the door.  After testing the swing and squareness, it just needed some shims on the side and to be screwed into the studs.  A bit of caulk around the molding on the outside, and voilà!  We’ll start the trim whenever we get another dry day.